Experience the Fraser Multi Use Pathway for Maple Ridge
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 19, 2022
2023202420252026
Built
Approved 6 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- City of Maple Ridge
- Construction start
- Mar 21, 2023(actual)
- Construction end
- Mar 31, 2026(actual)
Against the original forecast
- Construction start6 months lateforecast Sep 12, 2022
- Construction end2.8 years lateforecast Jun 30, 2023
Also in Maple Ridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63820 in the federal list. How to read these figures.