Back to projects

New Brunswick Museum Planning – Phase 1

Saint John, New Brunswick

underwayCapacity BuildingGIS
Federal contribution
$4.1M
$4,075,739
Federal share49%

of $8.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 23, 2022
today
20232024202520262027
BuiltForecast
Program
Green Infrastructure Stream
Ultimate recipient
New Brunswick Museum
Construction start
Jan 3, 2023(actual)
Construction end
Mar 31, 2027(forecast)

Against the original forecast

  • Construction start6 months lateforecast Jul 12, 2022