Installation of a Concrete Active Transportation Pathway on the south side of Saskatchewan Ave. W. from Elm St. to West Park School
Federal contribution
$92,400
Federal share60%
of $154.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 17, 2023
202320242025
Built
Approved 11 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- City of Portage La Prairie
- Construction start
- Jun 17, 2024(actual)
- Construction end
- Dec 31, 2024(actual)
Against the original forecast
- Construction start13 months lateforecast May 29, 2023
- Construction end18 months lateforecast Jul 14, 2023
Also in Portage la Prairie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64154 in the federal list. How to read these figures.