Sussex Avenue Sidewalk
Federal contribution
$201,075
Federal share36%
of $560.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 13, 2025
2023202420252026
Built
Approved 2.2 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Riverview
- Construction start
- Sep 2, 2025(actual)
- Construction end
- Dec 19, 2025(actual)
Against the original forecast
- Construction start3 months lateforecast May 31, 2025
- Construction end3 months earlyforecast Mar 31, 2026
Also in Riverview
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64354 in the federal list. How to read these figures.