Creating a Connected Community for the Town of Olds, Alberta
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 26, 2024
202320242025
Built
Approved 2 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Olds
- Construction start
- Sep 1, 2022(actual)
- Construction end
- Jul 1, 2025(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Oct 15, 2022
- Construction end2.3 years lateforecast Feb 28, 2023
Also in Olds
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64369 in the federal list. How to read these figures.