Detailed Design for Annandale Lands Trail Network
Federal contribution
$50,000
Federal share40%
of $125.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 6, 2024
20232024
BuiltForecast
Approved 2.2 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Ajax
- Construction start
- Mar 1, 2023(forecast)
- Construction end
- Dec 31, 2023(forecast)
Also in Ajax