Technical evaluation of the costs associated with the development of a dedicated bicycle path between Saint-Hyacinthe and Farnham

Saint-Hyacinthe, Quebec

completeCapacity BuildingATF
Federal contribution
$50,000
Federal share100%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 5, 2025
202320242025
Built

Approved 2.5 years before the announcement.

Program
Active Transportation Fund
Ultimate recipient
RM of Maskoutains
Construction start
Mar 27, 2023(actual)
Construction end
Jan 1, 2025(actual)

Against the original forecast

  • Construction start11 months lateforecast May 1, 2022
  • Construction end21 months lateforecast Mar 31, 2023