Accessible Paved Pathways in Centennial Park, Manotick Ontario

Ottawa, Ontario

completeCapacity BuildingATF
Federal contribution
$31,178
Federal share62%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 14, 2023
20232024
Built

Approved 17 months before the announcement.

Program
Active Transportation Fund
Construction start
Apr 1, 2023(actual)
Construction end
Jan 1, 2024(actual)

Against the original forecast

  • Construction start7 months lateforecast Sep 12, 2022
  • Construction end6 months lateforecast Jun 26, 2023