Shelbourne Street Improvements Project - Phase 3, District of Saanich, BC

Saanich, British Columbia

completeActive TransportationATF
Federal contribution
$2.6M
$2,580,000
Federal share27%

of $9.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 17, 2023
20232024
Built

Approved 5 months before the announcement.

Program
Active Transportation Fund
Construction start
Aug 26, 2023(actual)
Construction end
Sep 13, 2024(actual)

Against the original forecast

  • Construction start5 months earlyforecast Jan 31, 2024
  • Construction end14 months earlyforecast Oct 31, 2025

Also in Saanich

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64506 in the federal list. How to read these figures.