Sidewalk Infill Strategy Completion
Federal contribution
$26,190
Federal share52%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2023
20232024
Built
Approved 11 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- City of Saint John
- Construction start
- Apr 11, 2023(actual)
- Construction end
- Jun 30, 2024(actual)
Against the original forecast
- Construction start3 months lateforecast Jan 1, 2023
- Construction end12 months lateforecast Jul 1, 2023
Also in Saint John