Back to projects

Sidewalk Infill Strategy Completion

Saint John, New Brunswick

completeCapacity BuildingATF
Federal contribution
$26,190
Federal share52%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2023
20232024
Built

Approved 11 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
City of Saint John
Construction start
Apr 11, 2023(actual)
Construction end
Jun 30, 2024(actual)

Against the original forecast

  • Construction start3 months lateforecast Jan 1, 2023
  • Construction end12 months lateforecast Jul 1, 2023

Also in Saint John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64519 in the federal list. How to read these figures.