Accessible Active Transportation Crossing of the Rideau Canal at Hartwells Locks, Ottawa, ON
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 19, 2023
202320242025
BuiltForecast
Approved 12 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Mar 1, 2023(forecast)
- Construction end
- Mar 1, 2025(forecast)
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64537 in the federal list. How to read these figures.