completeCapacity BuildingATF
Federal contribution
$50,000
Federal share56%

of $90.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 19, 2022
202320242025
Built

Approved 6 months before the announcement.

Program
Active Transportation Fund
Construction start
Feb 16, 2023(actual)
Construction end
Mar 24, 2025(actual)

Against the original forecast

  • Construction start5 months lateforecast Sep 5, 2022
  • Construction end18 months lateforecast Sep 29, 2023