Back to projects

Cycling and hiking trail infrastructure improvement for Spruce Lake, New Brunswick

Saint John, New Brunswick

underwayActive TransportationATF
Federal contribution
$513,883
Federal share60%

of $856.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 11, 2023
2023
BuiltForecast

Approved 9 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
The Coastal Link Trail Inc.
Construction start
May 1, 2023(actual)
Construction end
Nov 1, 2023(forecast)

Against the original forecast

  • Construction start2 weeks earlyforecast May 15, 2023

Also in Saint John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64594 in the federal list. How to read these figures.