Wye Lake Trail Enhancements and Signpost Forest Multi-Use Pathway, Watson Lake, Yukon
Federal contribution
$43,440
Federal share100%
of $43.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 10, 2024
20232024
Built
Approved 18 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Watson Lake
- Construction start
- Mar 31, 2022(actual)
- Construction end
- Mar 31, 2023(actual)
Against the original forecast
- Construction start2 months earlyforecast Jun 1, 2022
- Construction end7 months lateforecast Aug 31, 2022
Also in Watson Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64619 in the federal list. How to read these figures.