Get Outside: Iqaluit Trails Plan, Iqaluit, Nunavut
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 12, 2023
2023
Built
Approved 7 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- City of Iqaluit
- Construction start
- Jan 18, 2023(actual)
- Construction end
- Jun 30, 2023(actual)
Against the original forecast
- Construction start9 months lateforecast May 1, 2022
- Construction end3 months lateforecast Mar 31, 2023
Also in Iqaluit
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64624 in the federal list. How to read these figures.