Neeginan Centre Retrofit
Federal contribution
$21.2M
$21,163,956
Federal share100%
of $21.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 2, 2024
2023202420252026
BuiltForecast
Approved 23 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Neeginan Centre Inc.
- Construction start
- May 14, 2024(actual)
- Construction end
- May 26, 2026(forecast)
Against the original forecast
- Construction start2.6 years lateforecast Oct 1, 2021
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64697 in the federal list. How to read these figures.