Journey in the Heart of the Homeland
Federal contribution
$23.2M
$23,154,166
Federal share71%
of $32.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 15, 2022
today
20232024202520262027
BuiltForecast
Approved 5 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Manitoba Metis Federation
- Construction start
- Oct 18, 2023(actual)
- Construction end
- Dec 26, 2026(forecast)
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64698 in the federal list. How to read these figures.