Victoria Campus Community Centre

Waterloo, Ontario

underwayAffordable And Temporary HousingGICB
Federal contribution
$2.2M
$2,244,000
Federal share26%

of $8.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 19, 2024
202320242025
BuiltForecast

Approved 2.3 years before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
May 25, 2024(actual)
Construction end
Aug 31, 2025(forecast)

Against the original forecast

  • Construction start11 months lateforecast Jul 1, 2023

Also in Waterloo

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64806 in the federal list. How to read these figures.