Back to projects

Ka Ni Kanichihk Community Campus Expansion

Winnipeg, Manitoba

underwayOtherGICB
Federal contribution
$6.3M
$6,311,657
Federal share50%

of $12.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 22, 2023
202320242025
BuiltForecast

Approved 9 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Ultimate recipient
Ka Ni Kanichihk Inc.
Construction start
Sep 27, 2023(actual)
Construction end
Jul 15, 2025(forecast)

Also in Winnipeg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64843 in the federal list. How to read these figures.