Lift Station Upgrades - Church Street

Deer Lake, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$115,405
Federal share40%

of $288.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 21, 2025
202320242025
Built

Approved 2.6 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Deer Lake
Construction start
Apr 5, 2025(actual)
Construction end
Oct 11, 2025(actual)

Against the original forecast

  • Construction start2 months earlyforecast Jun 15, 2025
  • Construction end8 weeks lateforecast Aug 15, 2025