Manitoba Theatre for Young People Accessibility and Environmental Upgrades

Winnipeg, Manitoba

completeCultureGICB
Federal contribution
$1.3M
$1,349,740
Federal share57%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 20, 2024
2023202420252026
Built

Approved 18 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
Aug 12, 2024(actual)
Construction end
Dec 25, 2025(actual)

Against the original forecast

  • Construction start15 months lateforecast May 9, 2023
  • Construction end4 weeks lateforecast Nov 30, 2025