Library Square Energy Retrofit

Vancouver, British Columbia

completeCultureGICB
Federal contribution
$2.4M
$2,382,080
Federal share43%

of $5.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 10, 2024
202320242025
Built

Approved 22 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Ultimate recipient
City of Vancouver
Construction start
Jul 4, 2023(actual)
Construction end
Feb 28, 2025(actual)

Against the original forecast

  • Construction start4 months lateforecast Mar 1, 2023
  • Construction end7 months lateforecast Jul 31, 2024