Ducks Unlimited embraces a green and more accessible future

Fredericton, New Brunswick

completeOtherGICB
Federal contribution
$188,600
Federal share80%

of $235.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 16, 2023
20232024
Built

Approved 15 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Ultimate recipient
Ducks Unlimited Canada
Construction start
Jan 10, 2023(actual)
Construction end
Mar 31, 2024(actual)

Against the original forecast

  • Construction start8 months lateforecast May 1, 2022
  • Construction end12 months lateforecast Mar 31, 2023