Environmental Assessments & Compensation Plan - West Bay Connector
Federal contribution
$50,000
Federal share88%
of $56.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 16, 2023
2023
BuiltForecast
Approved 2 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Adams Lake Indian Band
- Construction start
- Sep 1, 2022(forecast)
- Construction end
- Mar 31, 2023(forecast)
Also in Chase