Back to projects

Mill Market Sault Ste Marie Community Facility

Sault Ste. Marie, Ontario

completeOtherGICB
Federal contribution
$1.7M
$1,711,596
Federal share50%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2023
2023
Built

Approved 2 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Ultimate recipient
Mill Market Sault Ste Marie
Construction start
Apr 11, 2022(actual)
Construction end
Oct 31, 2023(actual)

Against the original forecast

  • Construction start7 months earlyforecast Nov 7, 2022
  • Construction end7 months lateforecast Mar 31, 2023

Also in Sault Ste. Marie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65544 in the federal list. How to read these figures.