Back to projects

Efficiency and Accessibility Upgrades

Fredericton, New Brunswick

underwayOtherGICB
Federal contribution
$1.0M
$1,000,000
Federal share79%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 11, 2023
today
20232024202520262027
BuiltForecast

Approved 5 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
Jul 1, 2024(actual)
Construction end
Jun 30, 2027(forecast)

Against the original forecast

  • Construction start3 months lateforecast Apr 1, 2024

Also in Fredericton