Cemetery Naturalized Stormwater Pond and Drainage
Federal contribution
$1.0M
$1,000,000
Federal share41%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 18, 2025
today
20252026202720282029
BuiltForecast
Approved 12 months before the announcement.
- Program
- Natural Infrastructure Fund
- Ultimate recipient
- City of Brandon
- Construction start
- May 1, 2026(forecast)
- Construction end
- Dec 31, 2028(forecast)
Also in Brandon