Centennial Field Skateboard Park Upgrade

Grand Falls-Windsor, Newfoundland and Labrador

completeRecreationCCRIS
Federal contribution
$147,606
Federal share33%

of $442.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
20242025
Built

Approved 23 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Town of Grand Falls-Windsor
Construction start
Sep 19, 2023(actual)
Construction end
Sep 28, 2023(actual)

Against the original forecast

  • Construction start3 months earlyforecast Jan 1, 2024
  • Construction end6 months earlyforecast Mar 31, 2024

Also in Grand Falls-Windsor

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66497 in the federal list. How to read these figures.