Electrification of Transit System
Federal contribution
$1.0M
$1,027,280
Federal share40%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 8, 2024
today
20242025202620272028
BuiltForecast
Approved 9 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Sault Ste. Marie
- Construction start
- Mar 25, 2024(actual)
- Construction end
- Mar 31, 2028(forecast)
Also in Sault Ste. Marie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66802 in the federal list. How to read these figures.