Transit Facility and Equipment Upgrades
Federal contribution
$1.1M
$1,080,800
Federal share40%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 8, 2024
today
20242025202620272028
BuiltForecast
Approved 11 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Sault Ste. Marie
- Construction start
- Feb 27, 2024(actual)
- Construction end
- Mar 31, 2028(forecast)
Also in Sault Ste. Marie