Back to projects

Purchase of Rolling Stock Assets

Sault Ste. Marie, Ontario

underwayPublic TransitPTIS
Federal contribution
$995,960
Federal share40%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 8, 2024
today
20242025202620272028
BuiltForecast

Approved 11 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of Sault Ste. Marie
Construction start
Jul 3, 2024(actual)
Construction end
Dec 31, 2027(forecast)

Also in Sault Ste. Marie