Education and Child Care - School District 41 - Edmonds Community Elementary Ventilation Improvements
Federal contribution
$800,101
Federal share80%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 10, 2023
2024
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- School District 41 - Edmonds Community Elementary
- Construction start
- Aug 1, 2023(actual)
- Construction end
- May 31, 2024(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2023
- Construction end10 months earlyforecast Mar 31, 2025
Also in Burnaby
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66837 in the federal list. How to read these figures.