BC Housing - Westwood Court
Prince George, British Columbia
Federal contribution
$924,480
Federal share80%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2023
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- BC Housing Management Commission
- Construction start
- Jul 21, 2023(actual)
- Construction end
- Oct 7, 2023(actual)
Against the original forecast
- Construction start6 months lateforecast Feb 1, 2023
- Construction end15 months earlyforecast Dec 31, 2024
Also in Prince George
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66849 in the federal list. How to read these figures.