BC Housing - Hotel Canada

Vancouver, British Columbia

completeVentilationCVRIS
Federal contribution
$299,600
Federal share80%

of $374.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 17, 2023
2024
Built

Approved 10 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 1, 2023(actual)
Construction end
Mar 31, 2024(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 31, 2023
  • Construction end3 months earlyforecast Jun 30, 2024