Oak Bay - Uplands Combined Sewer Separation

Oak Bay, British Columbia

underwayWastewaterGIS
Federal contribution
$3.5M
$3,535,580
Federal share40%

of $8.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 15, 2024
202420252026
BuiltForecast

Approved 10 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
District of Oak Bay
Construction start
Apr 24, 2024(actual)
Construction end
Jul 1, 2026(forecast)

Against the original forecast

  • Construction start2 months earlyforecast Jun 29, 2024