Oak Bay - Uplands Combined Sewer Separation
Federal contribution
$3.5M
$3,535,580
Federal share40%
of $8.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 15, 2024
202420252026
BuiltForecast
Approved 10 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- District of Oak Bay
- Construction start
- Apr 24, 2024(actual)
- Construction end
- Jul 1, 2026(forecast)
Against the original forecast
- Construction start2 months earlyforecast Jun 29, 2024
Also in Oak Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66920 in the federal list. How to read these figures.