Water Main Extension & Secondary Connection
Federal contribution
$632,421
Federal share50%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- District of Oak Bay
- Construction start
- Apr 24, 2017(actual)
- Construction end
- Dec 14, 2018(actual)
Against the original forecast
- Construction start4 months earlyforecast Sep 5, 2017
- Construction end6 weeks lateforecast Oct 31, 2018
Also in Oak Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49814 in the federal list. How to read these figures.