Uplands Combined Sewer Separation Project - Detailed Design

Oak Bay, British Columbia

completeWastewaterCWWF
Federal contribution
$168,597
Federal share50%

of $337.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
District of Oak Bay
Construction start
Aug 26, 2017(actual)
Construction end
Jun 29, 2018(actual)

Against the original forecast

  • Construction start17 months lateforecast Apr 1, 2016
  • Construction end3 months lateforecast Mar 31, 2018