Westsyde Road Multi-Use Pathway

Kamloops, British Columbia

underwayActive TransportationATF
Federal contribution
$738,000
Federal share100%

of $738.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 14, 2024
20242025
BuiltForecast

Approved 12 months before the announcement.

Program
Active Transportation Fund
Construction start
Aug 6, 2024(actual)
Construction end
Oct 24, 2025(forecast)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2024