Federal contribution
$738,000
Federal share100%
of $738.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 14, 2024
20242025
BuiltForecast
Approved 12 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Whispering Pines/Clinton Indian Band
- Construction start
- Aug 6, 2024(actual)
- Construction end
- Oct 24, 2025(forecast)
Against the original forecast
- Construction start3 months lateforecast May 1, 2024