Lions Manor Personal Care Home - Air Handling Unit Replacement #5
Federal contribution
$206,480
Federal share80%
of $258.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 19, 2023
20242025
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Province of Manitoba
- Construction start
- Feb 10, 2025(actual)
- Construction end
- Jul 31, 2025(actual)
Against the original forecast
- Construction start24 months lateforecast Feb 15, 2023
- Construction end8 months earlyforecast Mar 31, 2026