Saul & Claribel Simkin Centre - Replace Kitchen Condensing Unit
Federal contribution
$72,000
Federal share80%
of $90.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 19, 2023
20242025
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Province of Manitoba
- Construction start
- Oct 3, 2024(actual)
- Construction end
- Dec 31, 2024(actual)
Against the original forecast
- Construction start20 months lateforecast Feb 15, 2023
- Construction end15 months earlyforecast Mar 31, 2026
Also in Winnipeg