Pan Am Clinic - Building Management System Controls Upgrade
Federal contribution
$158,732
Federal share80%
of $198.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 21, 2025
today
20242025202620272028
BuiltForecast
Approved 2 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Province of Manitoba
- Construction start
- Mar 1, 2027(forecast)
- Construction end
- Dec 31, 2027(forecast)
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66951 in the federal list. How to read these figures.