Vancouver Airport Authority - Vancouver International Airport Low-Carbon Hot Water Systems
Federal contribution
$2.1M
$2,099,059
Federal share40%
of $5.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 15, 2023
today
20242025202620272028
BuiltForecast
Approved 6 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Vancouver Airport Authority
- Construction start
- Mar 31, 2024(actual)
- Construction end
- Dec 31, 2027(forecast)
Against the original forecast
- Construction start2 months earlyforecast Jun 5, 2024
Also in Vancouver
- Millennium Line Broadway Extension (TransLink)$888.4M
- Vancouver Convention and Exhibition Centre Expansion$222.5M
- Seismic Upgrade and Rehabilitation of Cambie Street Bridge in Vancouver, British Columbia$84.4M
- Rapid Transit Systems Rehabilitation and Maintenance$46.2M
- Rapid Transit Fleet Expansion - SkyTrain Network$44.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66989 in the federal list. How to read these figures.