Grace General Hospital - Critical Building Management Control System Upgrade Phase 2

Winnipeg, Manitoba

completeVentilationCVRIS
Federal contribution
$112,000
Federal share80%

of $140.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 19, 2023
2024
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Province of Manitoba
Construction start
Jun 1, 2023(actual)
Construction end
Aug 31, 2024(actual)

Against the original forecast

  • Construction start3 months lateforecast Feb 15, 2023
  • Construction end4 weeks lateforecast Jul 31, 2024