Upgrading to ventilation standards decay room #1043
Saint-Jean-sur-Richelieu, Quebec
Federal contribution
$92,000
Federal share80%
of $115.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 28, 2024
2024
Built
Approved 18 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux de la Montérégie-Centre
- Construction start
- Sep 1, 2023(actual)
- Construction end
- May 30, 2024(actual)
Against the original forecast
- Construction start2 months lateforecast Jul 1, 2023
- Construction end4 weeks earlyforecast Jun 30, 2024