City of Leduc - Annual Tree Purchase
Federal contribution
$112,000
Federal share80%
of $140.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 6, 2023
Built
Approved 6 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Leduc
- Construction start
- Jun 27, 2023(actual)
- Construction end
- Sep 30, 2023(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 15, 2023
- Construction end3 months lateforecast Jun 30, 2023
Also in Leduc
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67290 in the federal list. How to read these figures.