Lancaster Lagoon - Aeration System Renewal
Federal contribution
$1.5M
$1,540,000
Federal share40%
of $3.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
20242025
Built
Approved 21 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Saint John
- Construction start
- Apr 12, 2025(actual)
- Construction end
- Nov 6, 2025(actual)
Against the original forecast
- Construction start6 weeks lateforecast Mar 1, 2025
- Construction end8 weeks earlyforecast Dec 31, 2025
Also in Saint John