Work on stairwells
Federal contribution
$806,400
Federal share80%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2024
202420252026
Built
Approved 16 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de Laval
- Construction start
- May 20, 2023(actual)
- Construction end
- Nov 29, 2025(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Jun 15, 2023
- Construction end4 months earlyforecast Mar 31, 2026
Also in Laval
- The Société de transport de Laval garage expansion (Phase IV)$85.1M
- Acquisition of 94 Electric Buses$59.5M
- Updating drinking water treatment plants in Laval$46.8M
- Stabilization and revitalization work on the shore and Boulevard des Mille-Îles between Highway 25 and the eastern tip of Laval Island$25.3M
- Backflow controls of Monty sector - Laval$12.3M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67432 in the federal list. How to read these figures.