ECC - SD 52 - Roosevelt Park Elementary Ventilation Improvements
Prince Rupert, British Columbia
Federal contribution
$331,648
Federal share80%
of $414.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2023
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- School District 52 - Roosevelt Park Elementary
- Construction start
- Jun 25, 2023(actual)
- Construction end
- Oct 30, 2023(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 1, 2023
- Construction end7 weeks earlyforecast Dec 15, 2023
Also in Prince Rupert
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67726 in the federal list. How to read these figures.