Education and Child Care (ECC) - School District (SD) 57 - Peden Hill Elementary Ventilation Improvements
Prince George, British Columbia
Federal contribution
$373,808
Federal share80%
of $467.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2023
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- School District 57 - Peden Hill Elementary
- Construction start
- Jul 15, 2023(actual)
- Construction end
- Sep 15, 2023(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jun 1, 2023
- Construction end3 months earlyforecast Dec 15, 2023
Also in Prince George
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67727 in the federal list. How to read these figures.