City of Fredericton - Willie O'Ree Brine Pipe Replacement
Federal contribution
$130,655
Federal share33%
of $395.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
20242025
Built
Approved 19 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Fredericton
- Construction start
- Jul 10, 2023(actual)
- Construction end
- Oct 31, 2023(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2023
- Construction end2 months lateforecast Aug 31, 2023
Also in Fredericton
- University of New Brunswick - Justice Building Renewal$24.9M
- Awitgati Longhouse & Cultural Centre$18.6M
- New Brunswick Broadband$16.5M
- Fredericton - Core Water and Sewer Infrastructure Multi-Year Renewal$12.6M
- Multiple Natural and Structural Infrastructure Projects to Adapt to Pluvial and Fluvial Flood Events in Fredericton$11.4M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67883 in the federal list. How to read these figures.